The tilers were in yesterday to put in the kitchen backsplash glass tiles and the fireplace hearth. I also nabbed some additional photos of the stairs and the lawn, which is growing strong now.




The tilers were in yesterday to put in the kitchen backsplash glass tiles and the fireplace hearth. I also nabbed some additional photos of the stairs and the lawn, which is growing strong now.



The finish plumbing is now well underway. The sinks and faucets have been installed in most locations.
Also, the team is working hard on the staircase, which is complex and will take us right to the end of our schedule.


The countertops are in! They are all made of a quartz material.



The vertical grain bamboo flooring has been installed in the upstairs kids bedrooms and the master shower tile has now been completed after the “tile-in” storage shelves arrived from special order.


Things are cooking now. The great room fireplace stonework has been completed, the dirt has been hydroseeded, the outside stairs have been poured and most of the bathroom tile has been grouted. See for yourself.